California Waiver Through Date Examples
Use these examples to avoid over-waiving rights. The Through Date should match the labor/material period covered by the payment.
Example 1: Monthly Progress Billing
Invoice period: January 1, 2026 to January 31, 2026
Use Through Date: January 31, 2026
Do not use payment received date if work period ended earlier.
Example 2: Mid-Month Draw
Invoice period: February 1, 2026 to February 15, 2026
Use Through Date: February 15, 2026
If the draw only covers half the month, the Through Date should stop there.
Example 3: Final Payment
Final scope completion: March 20, 2026
Use Through Date: March 20, 2026
For final waivers, Through Date usually matches project completion date for billed scope.
Quick Rules
- Match Through Date to the covered work/material period, not assumptions.
- When in doubt, use a narrower date range to avoid over-releasing rights.
- Confirm your waiver type first in the California Waiver Selector.